Avista announced a pause in evaluating energy requests from new large data center developers, specifically halting negotiations for a previously announced 500MW data center. This decision follows significant community interest and concerns regarding the project. The company aims to take additional time to partner with governmental agencies for a coordinated planning process and consider stakeholder feedback, emphasizing transparency and long-term regional interests.
Key Highlights
- Avista pauses evaluation of energy requests from new large data center developers.
- Negotiations concerning energy service to a potential 500MW data center are now halted.
- Decision follows community interest and concerns regarding a previously announced MoU.
- Avista seeks additional time to partner with governmental agencies for coordinated planning.
- Company emphasizes transparency, thoughtfulness, and long-term regional interests.
- Existing customers will not pay for costs of serving new large customers.
- System reliability is non-negotiable, requiring engineering studies and upgrades.
- Any final service agreement must be reviewed and approved by state regulators.