Project UpdateJun 12, 2026, 05:21 PM
Hydro One seeks OEB approval for $430M Durham Kawartha Power Line
AI Summary
Hydro One Networks Inc. has filed a leave-to-construct application with the Ontario Energy Board (OEB) for the Durham Kawartha Power Line. This approximately $430 million investment will create a 55-kilometre double-circuit, 230-kilovolt transmission line between Clarington Transformer Station and Dobbin Transformer Station, expected to be in service by 2029. The project aims to support growth, enhance reliability, and will offer proximate First Nations a 50% equity stake through Hydro One's First Nation Equity Partnership Model.
Key Highlights
- Hydro One seeks Ontario Energy Board approval for the Durham Kawartha Power Line.
- The project is an approximately $430 million investment.
- It involves a 55-kilometre double-circuit, 230-kilovolt transmission line.
- The line will connect Clarington TS and Dobbin TS.
- Expected in-service date is 2029.
- Proximate First Nations will have the opportunity to invest in a 50% equity stake.
Price Impact
More from HRNNF