Project UpdateJun 2, 2026, 03:21 PM

Integra Appoints Ausenco for DeLamar Engineering; NEPA Process Begins

AI Summary

Integra Resources Corp. has appointed Ausenco Engineering USA South Inc. as the lead engineering partner for detailed engineering activities at its DeLamar Project in Idaho. Ausenco has engaged SLR Consulting for specialized heap leach engineering and mine planning. This move coincides with the launch of the 30-day public scoping period for the National Environmental Policy Act (NEPA) review process, following the Notice of Intent publication by the BLM on May 29, 2026. Detailed engineering is expected to continue through Q1 2027, with long-lead procurement starting in H2 2026, and the final EIS and ROD anticipated in H2 2027.

Key Highlights

  • Integra appointed Ausenco as lead engineering partner for the DeLamar Project.
  • Ausenco retained SLR Consulting for specialized heap leach engineering and mine planning.
  • Detailed engineering activities are underway and will continue through Q1 2027.
  • The NEPA public scoping period for the DeLamar Project started on June 2, 2026, for 30 days.
  • BLM published the Notice of Intent for the NEPA process on May 29, 2026.
  • Long-lead procurement activities are set to begin in H2 2026 and continue through 2027.
  • Final EIS and Record of Decision from the BLM are anticipated in H2 2027.