ExpansionMay 1, 2026, 04:12 PM
IREN Energizes 1.4GW Sweetwater 1 Data Center Site in Texas
AI Summary
IREN Limited announced the successful energization of its 1.4GW Sweetwater 1 data center site in Texas. This milestone connects the site's high-voltage substation to the ERCOT grid, marking a key step in developing the broader 2GW Sweetwater campus. Power delivery is expected to ramp progressively, reducing time-to-compute for customers and addressing power constraints in AI infrastructure deployment.
Key Highlights
- IREN successfully energized its 1.4GW Sweetwater 1 data center site in Texas.
- The site's high-voltage substation is now connected to the ERCOT grid.
- This marks a key milestone for the broader 2GW Sweetwater campus development.
- Power delivery at Sweetwater 1 is expected to ramp progressively.
- The energization helps reduce time-to-compute for customers.
- It addresses primary power constraints for AI infrastructure deployment.