LegalMay 22, 2026, 06:08 AM
KEPCO Faces New $1.1B Arbitration Claim from KHNP
AI Summary
KOREA ELECTRIC POWER CORP (KEPCO) announced that Korea Hydro & Nuclear Power Co., Ltd. (KHNP) has initiated arbitration at the Korean Commercial Arbitration Board (KCAB) seeking approximately USD 1.1 billion. The claim pertains to an operational support services contract for the UAE nuclear power plant project. This new arbitration replaces a previous proceeding before the London Court of International Arbitration, which is expected to be withdrawn. KEPCO plans to defend its case.
Key Highlights
- Korea Hydro & Nuclear Power Co., Ltd. (KHNP) initiated arbitration against KEPCO.
- The arbitration seeks payment of approximately USD 1.1 billion (KRW 1,661 billion).
- The claim relates to an operational support services contract for the UAE nuclear power plant project.
- The amount claimed represents 3.37% of KEPCO's total equity (KRW 49,323 billion as of fiscal year 2025).
- The arbitration was filed with the Korean Commercial Arbitration Board (KCAB) on May 21, 2026.
- KEPCO plans to defend its case through arbitration counsel.
- This new arbitration replaces a previous proceeding before the London Court of International Arbitration (LCIA), which is expected to be withdrawn.