Vizsla Silver Delays Panuco Production to H2 2028; Launches Foundation

AI Summary

Vizsla Silver Corp. has provided an update on its Panuco silver-gold project in Mexico, with engineering approximately 50% complete and 85% of process plant equipment ordered. The company anticipates first silver production in the second half of 2028, a delay from the previous H2 2027 target. Vizsla Silver is also establishing the Vizsla Foundation with an initial commitment of US$5 million to support local communities.

Key Highlights

  • Vizsla Silver targets first silver production at Panuco project for H2 2028, revised from H2 2027.
  • Engineering for the Panuco project is approximately 50% complete.
  • Approximately 85% of process plant equipment for Panuco has been ordered.
  • Vizsla Foundation to be established with an initial US$5 million contribution.
  • The November 2025 Feasibility Study outlined an after-tax NPV of US$1.8 billion and an IRR of 111%.