New Launch2 April 2026 at 12:11 pm
Godawari Power and Ispat Receives Consent to Operate 6.91 MW Waste Heat Recovery Based Power Plant
AI Summary
Godawari Power and Ispat Ltd. has announced the receipt of Consent to Operate for a 6.91 MW Waste Heat Recovery Based Power Plant situated at Siltara Industrial Area, Raipur, Chhattisgarh. The plant, which utilizes waste heat from the company's existing Integrated Steel plant, has started its trial run and is expected to commence commercial operations by the end of April 2026.
Key Highlights
- Godawari Power and Ispat Ltd. has received Consent to Operate for a 6.91 MW Waste Heat Recovery Based Power Plant.
- The plant is situated at Siltara Industrial Area, Raipur, Chhattisgarh and utilizes waste heat from the company's existing Integrated Steel plant.
- The plant has started its trial run and is expected to commence commercial operations by the end of April 2026.
- The Consent to Operate was received from Chhattisgarh Environment Conservation Board.
- The power plant has a capacity of 6.91 MW.