Project UpdateJul 15, 2026, 09:26 AM
Aya Gold & Silver Advances Boumadine Project; Updated PEA in H2-2026
AI Summary
Aya Gold & Silver Inc. is progressing with its Boumadine Project, with the Feasibility Study (FS) advancing as planned and an Updated Preliminary Economic Assessment (PEA) on track for release in H2-2026. The company has completed 102,111 meters of infill drilling year-to-date and is preparing for competitive tenders for mining services and processing plant construction. Early works are planned to start by year-end, with the full FS expected to be completed by H2-2027. The company also announced its Q2-2026 financial results release date.
Key Highlights
- Boumadine Project Feasibility Study (FS) is progressing as planned.
- Updated Preliminary Economic Assessment (PEA) for Boumadine is on track for H2-2026 release.
- 102,111 meters of infill drilling completed year-to-date for the FS.
- Competitive tender for open pit mining contract expected to be completed in H1-2027.
- Shortlist for processing plant construction partner to be determined by year-end.
- Feasibility Study completion planned for H2-2027.
- Q2-2026 financial results to be released on August 13, 2026.