Project UpdateJul 7, 2026, 06:02 AM

Highlander Silver Updates Corani Project Development Milestones

AI Summary

Highlander Silver Corp. provided a photo update on the significant progress at its Corani Silver Project in Peru. Key milestones include a workforce exceeding 300, led by an experienced project management team, and ongoing construction of camp facilities, earthworks, and internal/external roads. The company also reported that substation construction is underway, with the transmission line set to commence in August, and long-lead-time orders to be placed in the same month.

Key Highlights

  • Workforce at Corani Silver Project surpasses 300 team members, with local hiring emphasis.
  • Project management team led by Carlos Ojeda, VP & General Manager, with 25+ years experience.
  • Camp and facility construction is currently underway at the site.
  • Preliminary earthworks for site infrastructure, pits, and collection ponds are in progress.
  • Internal and external access road construction is underway.
  • Substation construction is underway, with the transmission line scheduled to begin in August.
  • Long-lead-time orders for the project are planned to be placed in August.