AGI Greenpac to Expand Container Glass and Speciality Glass Facilities by 50 TPD Each

AI Summary

AGI Greenpac Ltd is undertaking de-bottlenecking exercises to revamp its Container Glass Facility from 1,850 TPD to 1,900 TPD and enhance the Speciality Glass Facility from 154 TPD to 200 TPD. The expansion is estimated to cost Rs. 47 crore and is expected to be commissioned by March 2026. The increased capacity will enable the company to meet high-volume demand in alco-beverage, food, pharma, chemical, and other premium markets such as cosmetics, perfumery, and luxury beverages.

Key Highlights

  • AGI Greenpac to expand Container Glass Facility from 1,850 TPD to 1,900 TPD
  • Speciality Glass Facility to be enhanced from 154 TPD to 200 TPD
  • Estimated capital expenditure of Rs. 47 crore
  • Expansion expected to be commissioned by March 2026
  • Increased capacity aimed at meeting high-volume demand in various industries