BHEL Secures LOI from MB Power for 1x800 MW Anuppur Thermal Power Project Equipment Supply
AI Summary
Bharat Heavy Electricals Limited (BHEL) has accepted a Letter of Intent (LOI) from MB Power (Madhya Pradesh) Limited for the supply of equipment, including Boiler, Turbine, and Generator, for the 1x800 MW Anuppur Thermal Power Project. The contract agreement is to be entered into shortly, with the Boiler and Turbine Generator to be manufactured at BHEL's Trichy and Haridwar plants respectively. The supply completion schedule is 58 months, and the approximate consideration is 2600 Cr. excl. GST.
Key Highlights
- BHEL accepts LOI from MB Power for 1x800 MW Anuppur Thermal Power Project
- Equipment supply includes Boiler, Turbine, and Generator
- Contract agreement to be entered into shortly
- Boiler and Turbine Generator to be manufactured at BHEL's Trichy and Haridwar plants
- Supply completion schedule of 58 months, and approximate consideration of 2600 Cr. excl. GST