Bondada Engineering Limited has successfully commissioned 56.9 MW of solar projects for Paradigm IT and MAHAGENCO across various clusters located in Hingoli, Dhule, Sambhajinagar, and Jalgaon (Maharashtra) as on 31st October 2025. This achievement marks a significant milestone in advancing the National Renewable Energy Mission, despite challenging monsoon conditions. The successful commissioning has pushed the company's cumulative commissioned capacity to over 1 GW, reaffirming its commitment to a greener planet and India’s clean energy goals, in line with the Company’s Vision 2030.

Key Highlights

  • Commissioning of 56.9 MW solar projects for Paradigm IT and MAHAGENCO
  • Milestone achievement in advancing the National Renewable Energy Mission
  • Cumulative commissioned capacity crossed the 1 GW milestone
  • Despite challenging monsoon conditions, timely commissioning achieved
  • Reaffirming commitment to a greener planet and India’s clean energy goals