Ceigall India: Ayodhya Bypass Project Achieves 35% Progress

AI Summary

Ceigall India Ltd's subsidiary, Ceigall Ayodhya Bypass Private Limited, has achieved 35% physical progress on the Southern Ayodhya Bypass project as of May 7, 2026. This milestone, verified by the Independent Engineer (IE) on May 12, 2026, was reached 92 days ahead of schedule. The project involves the construction of a 4/6 lane bypass spanning 32.172 km in Uttar Pradesh.

Key Highlights

  • Ceigall's Ayodhya Bypass project achieves 35% physical progress.
  • Project milestone reached 92 days ahead of schedule.
  • The project is executed through Ceigall Ayodhya Bypass Private Limited.
  • Independent Engineer verified the progress on May 12, 2026.