STOCKWATCH
·
Consulting Services
Deals19 Dec 2025, 12:33 pm

DMR Engineering Receives Work Order for Preparation of DPR of 99 MW Ting Ting Hydro Project in Sikkim

AI Summary

DMR Engineering Ltd. has received a work order for Preparation of Detailed Project Report (DPR) of 99 MW Ting Ting Hydro Project in the state of Sikkim, India. The contract period is 10 months for an aggregate amount of Rs. 74,50,000/- (Rupee Seventy-Four Lakh Fifty Thousand only), exclusive of GST amount.

Key Highlights

  • DMR Engineering received a work order for the preparation of DPR of 99 MW Ting Ting Hydro Project in Sikkim.
  • The contract period is 10 months for an aggregate amount of Rs. 74,50,000/- exclusive of GST.
  • The order was awarded by Sangamam Power Projects Private Limited.
  • The project is an engineering consultancy service.
  • The order is not a related party transaction.
DMR
Consulting Services
DMR Hydroengineering & Infrastructures Ltd

Price Impact