GAIL (India) Ltd. Revises Completion Schedule for Durgapur-Haldia & Dhamra Haldia Pipeline Sections

AI Summary

GAIL (India) Ltd. has announced a revision in the completion schedule for the Durgapur-Haldia & Dhamra Haldia pipeline sections of the Integrated Jagdishpur-Haldia-Bokaro-Dhamra Pipeline Project. The Kolkata-Haldia section and the Dhamra-Haldia (W.B.) section, previously scheduled for completion in March 2025, have been revised to December 2025. The delay is due to issues with Right of Use (RoU) and fisheries front availability. The revision was approved by the Board of Directors in a meeting held on April 9, 2025.

Key Highlights

  • GAIL (India) Ltd. revises completion schedule for Durgapur-Haldia & Dhamra Haldia pipeline sections.
  • Completion of Kolkata-Haldia section and Dhamra-Haldia (W.B.) section rescheduled from March 2025 to December 2025.
  • Revision due to delay in Right of Use (RoU) and fisheries front availability.
  • Decision approved by the Board of Directors in a meeting on April 9, 2025.
  • GAIL (India) Ltd. complies with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.