STOCKWATCH
·
Gas Transmission/Marketing
Deals23 Jun 2025, 01:54 pm

Gail (India) Ltd Revises Completion Schedule for Srikakulam Angul Pipeline Project to December 2025

AI Summary

Gail (India) Ltd has revised the completion schedule for its Srikakulam Angul Pipeline Project from June 2025 to December 2025. The main line of 422 Km has been mechanically completed and commissioning has started. However, the spur line of 322 Km has been affected due to delays in obtaining forest permission. Only 45 Km out of the total required permission of 56 Km has been received so far. The revision was approved in a Board of Directors meeting on June 23, 2025.

Key Highlights

  • Gail (India) Ltd revises completion schedule for Srikakulam Angul Pipeline Project to December 2025
  • Main line of 422 Km mechanically completed and commissioning started
  • Spur line of 322 Km affected due to delay in forest permission
  • Only 45 Km out of 56 Km required forest permission received
  • Revision approved in Board of Directors meeting on June 23, 2025
GAIL
Gas Transmission/Marketing
GAIL (INDIA) LTD.

Price Impact