Project Update3 Jan 2026, 04:46 pm

Gail (India) Ltd Revises Completion Schedule for Srikakulam Angul Pipeline Project to June 2026

AI Summary

Gail (India) Ltd has revised the completion schedule for its Srikakulam Angul Pipeline Project. The main pipeline of 422 km has been commissioned on 26-09-2025, while 280 km of the 322 km spur line has been completed. The remaining 56 km of the spur line was delayed due to the late receipt of Forest working permission. The permission has been received progressively and tree cutting is underway. The revision was approved by the Board of Directors in a meeting on 03.01.2026.

Key Highlights

  • Gail (India) Ltd revises completion schedule for Srikakulam Angul Pipeline Project to June 2026
  • Main pipeline of 422 km commissioned on 26-09-2025
  • 280 km of 322 km spur line completed
  • Delay in receipt of Forest working permission for 56 km of spur line
  • Revision approved by the Board of Directors in a meeting on 03.01.2026
GAIL
Gas Transmission/Marketing
GAIL (INDIA) LTD.

Price Impact