Gujarat Natural Resources Ltd. (GNRL) and its step-down subsidiary, GNRL Oil & Gas Limited (GOGL), have successfully completed the third well, K#13, in the Kanawara field. This well has now been brought into commercial production, expected to increase the overall commercial production from the Kanawara field by 70-100 barrels of oil per day (BOPD). The drilling and completion of Well K#13 experienced delays due to the extended monsoon season. The drilling of the fourth well, K#17, is currently underway, targeting a depth of 1,700 meters and anticipated to be put into commercial production by the first week of November 2025.

Key Highlights

  • GNRL and GOGL have successfully completed the third well, K#13, in the Kanawara field.
  • Well K#13 has been brought into commercial production, increasing the overall commercial production by 70-100 BOPD.
  • The drilling and completion of Well K#13 were delayed due to the extended monsoon season.
  • The drilling of the fourth well, K#17, is currently underway with a target depth of 1,700 meters.
  • Well K#17 is expected to be put into commercial production by the first week of November 2025.