Business Update15 Mar 2025, 09:54 pm
Gujarat State Petronet Ltd Receives Approval for Capacity Expansion of High Pressure Gujarat Gas Grid
AI Summary
Gujarat State Petronet Ltd (GSPL) has received a letter dated 12th March, 2025 from the Petroleum and Natural Gas Regulatory Board (PNGRB) approving the expansion of capacity of GSPL's High Pressure Gujarat Gas Grid. The expansion involves the laying of the Anjar Palanpur Pipeline with a diameter of 30 inches and a length of 274 km. The pipeline will have a capacity of 12 MMSCMD and the capex for the project is limited to Rs. 2051.18 Crore. The expansion will increase the capacity of the High Pressure Gujarat Gas Grid to approximately 44.76 MMSCMD. The project is expected to be completed within 3 years from the date of this communication.
Key Highlights
- GSPL's proposal for capacity expansion of High Pressure Gujarat Gas Grid approved by PNGRB
- Expansion involves laying of Anjar Palanpur Pipeline with a diameter of 30 inches and a length of 274 km
- Pipeline to have a capacity of 12 MMSCMD and the capex for the project is limited to Rs. 2051.18 Crore
- Expansion will increase the capacity of the High Pressure Gujarat Gas Grid to approximately 44.76 MMSCMD
- Project completion schedule is 3 years from the date of this communication