Regulatory13 Jul 2026, 07:50 pm
Hariom Pipe Industries: Perundurai Unit Power Restored, Operations to Resume
AI Summary
Hariom Pipe Industries Ltd announced the suspension of a closure order and restoration of power supply to its Perundurai unit in Tamil Nadu. This follows an earlier temporary closure due to power disconnection. The Tamil Nadu Pollution Control Board (TNPCB) issued proceedings on July 13, 2026, suspending the closure directions and restoring power effective immediately. The suspension is valid until the next renewal on March 31, 2027, subject to compliance with stipulated conditions. The company is now taking steps to recommence operations at the unit. The exact financial implications of the temporary closure are currently not quantifiable.
Key Highlights
- Power supply restored to Perundurai unit.
- Closure order suspended by TNPCB until March 31, 2027.
- Operations at the Perundurai unit to recommence shortly.