Project Update11 Sept 2026, 08:30 pm
Juniper Green Energy commissions 40 MW wind capacity
AI Summary
Juniper Green Energy Limited announced that its wholly owned subsidiary, Juniper Green Spark Four Private Limited, has commissioned the entire 40 MW wind component of its 120 MW Wind Solar Hybrid Power Project. This commissioning brings the project's operational capacity to 82.01 MWp out of a planned 152 MWp. Following this, Juniper Green Energy's aggregate operational capacity now stands at approximately 2,679 MWp, along with ~500 MWh of Battery Energy Storage Systems (BESS). The commissioning was confirmed by Gujarat Energy Development Agency and Paschim Gujarat Vij Company Limited officials, with a formal certificate expected shortly.
Key Highlights
- 40 MW wind capacity commissioned for 120 MW hybrid project.
- Project's operational capacity reaches 82.01 MWp.
- Total operational capacity now ~2,679 MWp.
- Includes ~500 MWh of BESS.
- Commissioning confirmed by state agencies.