Expansion7 Oct 2026, 11:14 am
Patel Chem Specialities Ltd Starts Trial Batches at Talod Plant
AI Summary
Patel Chem Specialities Limited has completed the expansion of its Talod, Gujarat manufacturing facility, increasing annual production capacity from 720 MTPA to 4,500 MTPA. Trial batches have commenced, with commercial production expected shortly. This expansion, costing approximately ₹20 crore funded by bank loans and internal accruals, aims to meet anticipated demand growth and shorten delivery times. The expanded facility has the potential to generate ₹85-100 crore in annual revenue at peak utilization.
Key Highlights
- Talod plant expansion completed, capacity increased to 4,500 MTPA.
- Trial batches commenced, commercial production expected soon.
- Expansion cost ₹20 crore, funded by debt and internal accruals.
- Aims to meet demand growth and improve delivery schedules.
- Potential to generate ₹85-100 crore annual revenue at peak.