Deals6 Nov 2024, 11:52 pm
Rail Vikas Nigam Ltd Secures Order from East Central Railway Worth Rs 180 Crores
AI Summary
Rail Vikas Nigam Ltd has announced the receipt of a Letter of Acceptance from East Central Railway for a project involving the design, supply, erection, testing, and commissioning of 2x25KV feeder line along the track with 25KV OHE modification works. The project aims to meet a 3000 MT loading target for UP & DN line of Garwa Road -Mahadiya Section of Dhanbad Division under E.C. Railway. The cost of the work is Rs 180,00,96,810.08, including applicable taxes. The project is expected to be completed within 18 months from the date of award.
Key Highlights
- Rail Vikas Nigam Ltd has received an order from East Central Railway worth approximately Rs 180 crores.
- The project involves the design, supply, erection, testing, and commissioning of 2x25KV feeder line along the track with 25KV OHE modification works.
- The project aims to meet a 3000 MT loading target for UP & DN line of Garwa Road -Mahadiya Section of Dhanbad Division under E.C. Railway.
- The project is expected to be completed within 18 months from the date of award.
- The cost of the work is Rs 180,00,96,810.08, including applicable taxes.