Sanmit Infra Secures Rs.6,78,50,000 Micro Surfacing Work Order in Vaijapur

AI Summary

Sanmit Infra Ltd has secured a significant work order of 500000 SQMT Micro Surfacing Work in Vaijapur (Chh. Sambhaji Nagar) AU- 100A Project from Kalyan Toll Infrastructure Ltd. The contractor shall follow specific guidelines including providing and laying of Micro Surfacing course with polymer-modified cationic slo setting bitumen emulsion, ordinary Portland cement, chemical additives, and water. The project duration is 3 months, starting from 01/11/2025. Sanmit Infra Ltd will raise RA Bills after every 15 days, and the payment will be made in 5 working days from submission of bills after certification from KTIL's representative. The order is a domestic one, and the total consideration is Rs.6,78,50,000/- (including 18% GST).

Key Highlights

  • Sanmit Infra Ltd secures a work order of 500000 SQMT Micro Surfacing Work in Vaijapur from Kalyan Toll Infrastructure Ltd.
  • The project duration is 3 months, starting from 01/11/2025.
  • The total consideration for the work order is Rs.6,78,50,000/- (including 18% GST).
  • The contractor shall follow specific guidelines for providing and laying of Micro Surfacing course.
  • Sanmit Infra Ltd will raise RA Bills after every 15 days, and the payment will be made in 5 working days from submission of bills after certification from KTIL's representative.