SEPC Ltd Secures Rs. 180 Million Work Orders from Bajaj Energy Private Limited
AI Summary
SEPC Ltd has been awarded five work orders from Bajaj Energy Private Limited for Operation & Maintenance Services for their 2 x 45 MW Power Plants at Barkhera Kalan, Maqsoodpur, Khambarkhera, Utraula & Kundarki plants in Uttar Pradesh. The total value of these orders is Rs. 180000000/- (Rupees One Hundred and Eighty Millions only) with an execution period of 12 months each, starting from 14-05-2025.
Key Highlights
- SEPC Ltd secures Rs. 180 Million work orders from Bajaj Energy Private Limited
- Orders are for Operation & Maintenance Services for 2 x 45 MW Power Plants in Uttar Pradesh
- Execution period for each order is 12 months
- Orders commence from 14-05-2025