Expansion27 Aug 2025, 12:27 pm
Vaswani Industries Expands Billet Capacity, Progresses on Solar Power Projects
AI Summary
Vaswani Industries Ltd. has completed the expansion of its Billet manufacturing capacity from 66,000 MT per annum to 1,50,000 MT per annum. The company is currently in the trial run stage and will commence commercial production upon receipt of the Consent to Operate (CTO) from the Pollution Control Department. In addition, the company is progressing with its solar power projects in Chhattisgarh, with a total capacity of 66.50 MWp. The 16.25 MWp Gandai project is already operational, while the 13.75 MWp Mohbhatta project is expected to be operational by end of November 2025 due to delays caused by heavy rainfall. The 36.25 MWp Mohbhatta project is also in progress and expected to be operational during November-December 2025.
Key Highlights
- Completed expansion of Billet manufacturing capacity to 1,50,000 MT per annum
- Trial runs of expanded capacity in progress
- 16.25 MWp solar power project already operational
- 13.75 MWp solar power project delayed due to heavy rainfall, expected to be operational by end of November 2025
- 36.25 MWp solar power project in progress, expected to be operational during November-December 2025