Pace Digitek's fifth BOOT win: a ₹179.4 Cr Delhi BESS project paying a fixed ₹27.1 Cr a year for 12 years
BSES Rajdhani's LOI covers 57.5 MW/115 MWh at four Delhi grid stations under a 12-year BOOT model at a fixed tariff of ₹47.05 lakh/MW/year. The BOO/BOOT portfolio now stands at 3.32 GWh.
₹164.80 Oct 9 · +1.8% on the first session after the LOI
≈ ₹3,557 Cr 21.59 Cr shares outstanding
SMALL-CAP by market cap ≈ ₹3,557 Cr
₹179.4 Cr
₹1,794 million · 12-year BOOT
₹27.1 Cr
fixed tariff ₹47.05 lakh/MW/yr × 57.5 MW
−29.0%
adjusted high ₹231.95 (Oct 10, 2025)
An LOI from BSES Rajdhani for a 115 MWh battery in Delhi
Pace Digitek receives a ₹179.4 Cr LOI from BSES Rajdhani for a 57.5 MW/115 MWh BESS
Pace Digitek received a Letter of Intent aggregating to ₹1,794 million — i.e. ₹179.4 crore — from BSES Rajdhani Power Limited (BRPL) for design, supply, testing, installation, commissioning, operation and maintenance of a Battery Energy Storage System with an aggregate contracted capacity of 57.5 MW/115 MWh at four BRPL grid-station locations, for on-demand operation. The company's press release says the project will be developed in Delhi under a 12-year Build, Own, Operate and Transfer (BOOT) model with a project capital outlay of around ₹179.4 crore, scheduled to be executed within seven months.
Read:The press release calls this the company's fifth major utility-scale BOO/BOOT storage project, taking its BOO/BOOT portfolio to 3.32 GWh. Under the long-term Battery Energy Storage Service Agreement (BESSA) it describes, the company is to receive a fixed capacity tariff of ₹47.05 lakh per MW per year — annual contracted capacity revenue of ₹27.1 crore.
BSE filing — press release, Oct 8, 2026The structure matters as much as the headline number. This is not a one-off equipment sale: under the BOOT model the press release describes, Pace Digitek builds and owns the asset and earns a fixed capacity tariff — ₹47.05 lakh per MW per year across 57.5 MW — for operating it on demand over the 12-year term. The filing frames the ₹179.4 crore as the project's capital outlay, and the ₹27.1 crore as contracted annual capacity revenue under the BESSA.
Simple arithmetic on the filing's own numbers: ₹27.1 crore a year over the 12-year tenure is roughly ₹325 crore of contracted capacity revenue against the stated capital outlay of about ₹179.4 crore. That is gross contracted revenue, not a return figure — the filing does not state operating and maintenance costs, financing terms, or what happens to the asset's economics at transfer, so holders cannot compute a project return from the disclosure alone. What the disclosure does allow is sizing: a recurring ₹27.1 crore a year is about 1.2% of the company's annualised consolidated revenue run-rate (Q1 FY27 revenue of ₹555.36 crore × 4), an inference from the quarterly numbers below.
Third disclosed BESS award since late August
Subsidiary Lineage Power wins a ₹488.46 Cr BESS order from NTPC GE Power Services
Lineage Power Private Limited, the company's material subsidiary, received a Letter of Award aggregating to ₹4,884.61 million (inclusive of taxes) — i.e. ₹488.46 crore — from NTPC GE Power Services Private Limited (NGSL) for supply, delivery, testing and supervision of erection, testing and commissioning of 5.015 MWh BESS containers along with BMS and EMS, including a 12-year comprehensive maintenance contract.
Read:The October 8 press release cites this September win as part of the group's recent BESS momentum. Unlike the BSES BOOT project, this is a supply-plus-maintenance contract rather than an owned asset.
BSE filing — order intimation, Sep 21, 2026₹92.9 Cr Letter of Award from Kalpa Power for a 100 MWh BESS supply
A Letter of Award aggregating to ₹929.25 million (including GST) — i.e. ₹92.9 crore — from Kalpa Power Private Limited for supply and commissioning support of a 100 MWh Battery Energy Storage System. The August 21 intimation names Lineage Power, the material subsidiary, as the recipient; the August 24 press-release intimation describes the Company as having received it.
Read:The earliest of the three disclosed BESS awards in the pack's 60-day window, and like the NGSL win a supply contract rather than a BOOT asset.
BSE filing — order intimation, Aug 21, 2026The October 8 press release aggregates the picture: since the end of Q1 FY2027 the Pace Digitek group has secured ₹761 crore of additional orders across products and projects, and the company puts its total executable order book at over ₹11,500 crore. It describes participation across three models — BOO/BOOT ownership, EPC execution, and BESS supply — with manufacturing done through Lineage Power. The three disclosed awards above map onto exactly that split: one owned 12-year asset, two supply contracts.
The BSES award is another important milestone in the development of our Energy business and marks our fifth utility-scale BOO/BOOT storage project. It reinforces the capabilities we have built across BESS manufacturing, project execution and long-term asset operations.
— Venugopalrao Maddisetty, Chairman & Managing Director — press release, Oct 8, 2026
Order wins against a falling trend
At ₹164.80 the stock sits 29.0% below its adjusted 52-week high of ₹231.95 (set October 10, 2025) and 17.9% above the March 30 low of ₹139.81 — each order-win pop has come against a declining trend. Two volume spikes deserve a footnote. The September 22 session's +8.3% came on 2.67 crore shares, and the day's bulk-deal tape shows NK Securities Research and Microcurves Trading each buying and selling identical quantities (12.38 lakh and 13.35 lakh shares respectively) within the session — round trips, net flat. October 1 saw another 2.28 crore shares traded; on October 5 the exchange sought a clarification on the volume increase, and the company replied that there was no information or announcement, including any impending announcement, requiring disclosure.
Revenue up 51% YoY, margin and interest cost moving the other way
Q2 FY27 results are yet to be announced; the trading window closed October 1 pending the quarter and half-year results.
Q1 FY27 consolidated revenue of ₹555.36 crore was up 51.3% over Q1 FY26's ₹367.08 crore, with net profit up 14.3% to ₹62.51 crore — the gap explained by operating margin compressing from 21.8% to 15.5% and interest cost nearly tripling to ₹28.34 crore from ₹9.72 crore a year earlier. That interest line is the context for the funding side of the BOOT strategy: owning 3.32 GWh of storage assets requires capital, and on October 7 the company intimated a board meeting for October 12 to consider raising funds via non-convertible debentures on a private placement basis. The size and terms of any NCD issue would show how the build-out is being financed.
The next data points
Oct 12 board meeting
The board meets October 12 to consider an NCD issue on private placement. Size and coupon, if approved, are the first hard read on how the BOOT portfolio's capital outlay is funded.
LOI to agreement
The press release describes a long-term Battery Energy Storage Service Agreement with a fixed tariff and a seven-month execution schedule. The definitive agreement, and execution against that schedule, are the conversion markers for the ₹179.4 crore LOI.
Q2 FY27 results
The trading window closed October 1 until 48 hours after the quarter and half-year results. Margin and interest-cost trends after a period in which the group says it added ₹761 crore of orders since the end of Q1 FY2027, including the October 8 BSES LOI.
Further BOO/BOOT wins
The company says it will selectively expand the 3.32 GWh owned-storage portfolio. Each addition raises contracted revenue — and the capital the balance sheet must carry.
The BSES Rajdhani LOI is small against a stated order book of over ₹11,500 crore, but it is the clearest disclosure yet of what the company's BOOT model pays: a fixed ₹47.05 lakh per MW per year, ₹27.1 crore annually, for 12 years, on a ₹179.4 crore outlay. Holders can now put a contracted-revenue number on each megawatt of the 3.32 GWh owned portfolio's newest addition — something the earlier supply-order disclosures did not allow.
The open questions are on the cost side. The filings in view do not state project-level operating costs or financing terms, Q1 FY27 already shows interest expense rising faster than profit, and the October 12 board meeting on an NCD issue will indicate how the next round of asset-building is funded. The data suggests a business deliberately shifting toward long-term contracted assets; whether the economics clear the cost of the capital required is the question the coming disclosures should begin to answer.