NHPC LTD. · QQ2 FY-2027 · THE CALL

Strong revenue growth, tariff-gated profit upside ahead

The verdict, the claims that held up, the sharpest analyst exchanges, and the risks — the earnings call, decoded from the transcript.

Q2 FY27 resultsNHPCNHPC LTD.13 Nov 2026 · 6 min read
Verdict

Hold

confidence 6/10

Credibility

Grade B

Management hit revenue guidance implicitly (₹4,482 Cr claimed and delivered match). PAT discrepancy suggests incomplete disclosure of consolidation items or adjustments, not a miss, but transparency gap.

Short-term outlook

Optimistic

next 1–2 quarters

Long-term outlook

Optimistic

multi-year

Q2 delivered strong revenue (+33% YoY) and solid PAT growth (+36%), backed by real capacity additions (Subsansiri, Parbati-II, Teesta-V resumption). But path to FY28 EBITDA ₹10,000 Cr target hinges on tariff approvals still pending (Subsansiri interim, Parbati-II final Nov 11), and management understated Q2 PAT by ~₹109 Cr in call vs delivered result. Growth drivers are credible, but execution and tariff risks warrant caution.

₹4482.6 Cr

Revenue · +33.2% YoY

₹1657.6 Cr

Reported PAT · +35.9% YoY

Expanding

Margins · vs guidance: Corroborated

Did the claims hold up?

Management's claims vs. the numbers

Q2 revenue ₹4,482 Cr, up 33% YoY due to Subsansiri, Parbati-II, Teesta-V

MET

Delivered Q2 revenue ₹4,482.6 Cr, up 33.2% YoY — matches claim exactly

Q2 PAT ₹1,549 Cr reported (management discussed), 52% growth YoY

MISS

Delivered Q2 PAT ₹1,657.6 Cr, 35.9% YoY growth — management understated by ₹108.6 Cr or did not consolidate all gains

Subsansiri adding ₹132 Cr PBT in Q2; full-year AFC expected ₹5,500 Cr

MET

Supported by detailed project milestones; 5 units commissioned (1,250 MW), tariff petition hearing over, interim order pending — timeline credible

H1 generation 23,741 MUs, up 14% YoY; PAF 86.67% vs 81.10% prior year

MET

Operational data internally consistent and detailed per project; Subsansiri commissioning (higher water availability during ramp-up) explains margin lift

Receivables ₹4,283 Cr as of Sep 26; collection strong, only ₹290 Cr >45 days overdue

MET

Credible given LPS rules (2023) tightened payment discipline; out of reported ₹4,283 Cr, ₹1,573 Cr unbilled debtors (contract assets, not due yet)

Earnings quality

What changed since the last call

Deltas vs. the prior call

Subsansiri operational status

Upgrade

Moved from under-construction to 1,250 MW commissioned (5 units live). Q2 PBT ₹132 Cr baseline expected to grow as remaining units commission FY27 (2 units targeted). Impact visible in Q2 revenue (+₹1,117 Cr YoY, Subsansiri ~₹300 MU increment at higher tariff than base fleet).

Teesta-V commercial operation resumed

Upgrade

Returned to service July '26 after Oct 2023 flood damage. Q2 generation 859 MUs, revenue ₹150-160 Cr, PBT ₹99 Cr. Under-recovery vs design energy being absorbed; previously was a headwind, now contributing to revenue.

PAF (Plant Availability Factor) uplift

Upgrade

Q2 PAF 92.24% vs 78.58% prior year (+14 ppts). Driven by higher water availability during Subsansiri commissioning phase and Parbati-II ramp. Margin expansion from better asset utilization.

Receivables management post-LPS 2023 rules

Upgrade

Despite ₹4,283 Cr total receivables (up from ₹2,630 Cr), collection discipline tightened. Only ₹290 Cr >45 days overdue (6.8% of total). Old dues issue resolved; new unbilled position (₹1,573 Cr Subsansiri contract assets) is normal for growing projects.

Renewable energy strategy shift

Neutral

NHPC tendered 23,120 MW solar/wind capacity, awarded 73 projects. Only 9,000 MW PPAs signed (rest in negotiation). Strategy being reconfigured from vanilla solar to solar+BESS, solar+wind mixes per state needs. Execution slower than traditional hydro due to grid/government reluctance on commitment. No divestment planned, but growth timing uncertain.

The Q&A

Analysts pressed hard on tariff timing (Parbati-II, Subsansiri) and profitability bridge between new projects and consolidated PAT. Management held firm on timelines, detailed profit contribution by project, and explained capacity-ramp mechanics credibly. On receivables, management preemptively clarified unbilled debtors vs aged dues. Minor hedging on renewable energy strategy execution timelines (grid constraints, government commitment reluctance), but no defensive tone overall. Confidence maintained throughout.

The exchanges that mattered

Parbati-II tariff — Ragini Panday, Elara Capital

Answered

Next hearing Nov 11; expect final order soon. Unrecognized revenue ~₹500 Cr (20% of total). Expected AFC ₹2,400 Cr, PAT ~₹680 Cr at normal operation.

Subsansiri tariff and recovery — Ragini Panday, Elara Capital

Answered

Hearing over, order reserved for interim tariff. Booking revenue at 80% of petition. Expected AFC ₹5,500 Cr/year, PAT ₹1,500-1,600 Cr/year on full commissioning basis.

Teesta-V recovery — Ragini Panday, Elara Capital

Answered

Started commercial operation July '26. Q2 generation 859 MUs, revenue ₹150-160 Cr, PBT ₹99 Cr. Under-recovery reducing as operations normalize.

Adjusted PAT — Mohit Kumar, ICICI Securities

Answered

Yes, adjusted PAT = ₹1,549 Cr + ₹231 Cr = ₹1,780 Cr approx. (standalone basis). Growth 90% vs reported 52%, excluding one-time provision.

Subsansiri profit contribution breakdown — Mohit Kumar, ICICI Securities

Answered

Yes. During commissioning ramp, water availability higher than design. Subsansiri added ₹132 Cr PBT Q2, well above normalized 4-unit contribution. Typical 70% generation in H1, 30% in H2 seasonality.

Project award pipeline — Mohit Kumar, ICICI Securities

Partial

Dibang major contracts awarded; HM (hydro-mechanical) pending. Kamala CCEA approved, bidding ongoing. Savalkot expecting CCEA. Etalin all approvals secured, tendering initiated. PSPs in DPR/PFR stage; 2 expected to start work FY27. Timelines depend on government approvals.

Etalin payment to SJVN — Prashant Khirsagar, Unived Corporate Research

Answered

Not yet. Payment is contingent on PIB (Project Information Board) approval. PIB process initiated by Government of India, approval pending. Board has approved payment mechanism.

Solar/renewable strategy — Prashant Khirsagar, Unived Corporate Research

Answered

No divestment. CPSUs diversifying to renewables for hedge. NHPC tendered 23,120 MW, awarded 73 projects (9,000 MW PPAs signed, 5,000-7,070 MW more expected). Connectivity delays pushing some solar to Nov-Dec '27. Strategy shifting to solar+BESS, solar+wind mixes per state resource plans.

Receivables position — Keyur, PNB MetLife

Answered

As of Sep 26, total receivables ₹4,283 Cr (vs ₹2,630 Cr prior year). Of this, ₹1,573 Cr unbilled debtors (Subsansiri contract assets, billing deferred). Net billed dues ₹1,893 Cr, only ₹290 Cr >45 days overdue (6.8%). LPS 2023 rules tightened payment discipline; collection excellent.

Debt and EBITDA guidance — Keyur, PNB MetLife

Answered

Group debt ₹59,000 Cr split: ₹29,000 Cr in operations, ₹20,000 Cr in under-construction projects (bifurcated). Debt in construction projects refinanced, not a drag on operating cash. FY27 capex ₹14,300 Cr, FY28 onwards ₹14,000-15,000 Cr/year average. By FY28, EBITDA reaching ₹10,000 Cr post-Subsansiri. Internal accruals sufficient; no fresh equity needed.

Capex guidance forward — Kayur Asher, PNB MetLife

Answered

FY27 capex target ₹14,300 Cr achievable; H1 already ₹6,500 Cr spent. Next 10 years, average capex ₹14,000-15,000 Cr/year. Capex will drive EBITDA to ₹10,000 Cr. Internal accruals and balance-sheet financing sufficient; no fresh equity planned.

Parbati-II PBT for full year FY26 — Abhineet Anand, BNP Paribas

Answered

₹149 Cr loss in FY26. Q1 FY27 PBT ₹23 Cr, Q2 FY27 PBT ₹215 Cr (240 Cr approx. for full year). Parbati-III added ₹80 Cr. Three stations incremental PBT ₹460 Cr combined.

Teesta-V H2 profitability — Abhineet Anand, BNP Paribas

Partial

Typical 70% generation in H1, 30% in H2 seasonality applies. Q2 generated 859 MUs; expect similar generation in Q3, Q4 each (~100-150 Cr PBT range per quarter based on 100-150 Cr loss estimate for H2).

Transmission evacuation readiness — Mohit Kumar, ICICI Securities

Answered

Transmission responsibility of CTU (Central Transmission Utility). Master plan finalized; competitive bidding for transmission by PFC/REC. No problem evacuating power from Arunachal projects. Commissioning delays driven by project-side construction, not transmission.

Guidance

Forward guidance and management's confidence

FY28 incremental revenue from Subsansiri full-year: ₹5,500 Cr AFC baseline

Medium

1,250 MW now live; remaining units expected FY27. Tariff still awaiting interim order. Already booking at 80% of petition amount

FY28-FY29 incremental from Pakal Dul, Kiru, Rangit: Combined ~₹1,500 Cr AFC

Medium

Pakal Dul 1,000 MW; Kiru 624 MW; Rangit 120 MW targeting 2027-28 commissioning. Capex ~70-90% complete; execution on track

FY28 EBITDA target ₹10,000 Cr (vs current ₹6,000-7,000 Cr H1 run-rate)

Medium

Driven by Subsansiri ₹5,500 Cr AFC, Pakal Dul, Kiru, Parbati-II/III full-year ramp. Assumes tariff approvals (Subsansiri interim, Parbati-II final Nov 11). Post-commissioning, EBITDA margin 60-65%

FY27 capex target ₹14,300 Cr (H1 ₹6,500 Cr already achieved)

High

On track for second-half completion. Primary drivers: Subsansiri final units, Dibang, Teesta-VI, Uri-I, Dulhasti, Jalpower ramp

FY28 onwards capex ₹14,000-15,000 Cr/year average for next 10 years

Medium

10-year capex projection ₹1,11,000 Cr; requires ₹40,000 Cr equity (4% yearly avg). Management confident internal accruals sufficient

Risks the call surfaced

Ranked by how much they should concern a holder

Tariff regulatory

High

Subsansiri interim tariff order still pending; Parbati-II final hearing Nov 11. ₹500 Cr+ unrecognized revenue and EBITDA upside hinges on favorable CERC orders. 60-65% EBITDA margin assumptions depend on approved tariff levels.

Project execution

Medium

₹14,300 Cr FY27 capex target depends on Subsansiri final units, Dibang, Teesta-VI, Uri-I/Dulhasti timely commissioning. Weather (water availability, floods), supply-chain delays, tunneling risks (Teesta-VI cited as challenge) could push timelines.

Receivables and collection

Medium

Receivables ₹4,283 Cr vs ₹2,630 Cr prior year (+₹1,653 Cr). Of ₹4,283 Cr, ₹1,573 Cr unbilled debtors (Subsansiri contract assets). If billing is delayed or contract disputes arise (tariff petitions), cash flow could tighten.

Water availability and seasonality

Low

Management notes typical 70% generation H1, 30% in H2. Q2 PAF 92.24% benefited from higher water availability during Subsansiri commissioning ramp. H2 generation may normalize lower, impacting Q3/Q4 PAT.

Renewable energy execution

Medium

Solar/wind strategy shifted to solar+BESS, solar+wind. But grid connectivity issues, government reluctance to commit to 25-year PPAs, and resource-adequacy volatility are slowing award. H2 FY27 commissioning target at risk.

Management

Score 7/10. Detailed and data-rich; management provided specific project milestones, tariff numbers, P&L bridges. Some non-linearity in profitability narrative (reported ₹1,549 Cr vs delivered ₹1,657.6 Cr), but large part explained by ₹231 Cr Teesta-IV provision and consolidation. Transparent on contingencies (tariff pending, capex dependency). Strong track record on capex delivery (H1 ₹6,500 Cr on ₹14,300 Cr FY27 target) and project commissioning (Subsansiri 5 units live, Teesta-V resumed). Dibang on schedule (Nalla diversion achieved Oct '26). Some delays in renewable energy (grid connectivity) but hydro core execution credible.

What to watch next
  • 1 · Nov 11, 2026

    Parbati-II final tariff hearing; order expected soon (₹500 Cr unrecognized revenue at stake)

  • 2 · Q3 FY27

    Subsansiri interim tariff approval expected; ₹5,500 Cr AFC annual visibility

  • 3 · FY28

    Pakal Dul (1,000 MW), Kiru (624 MW), Rangit (120 MW) ramping; full Subsansiri impact

Growth drivers are credible, but execution and tariff risks warrant caution.