StockWatch
·
Power - Transmission
Deals19 Nov 2026, 02:24 pm

Adani Energy Solutions Wins Bihar Transmission Project

AI Summary

Adani Energy Solutions Limited (AESL) has secured a significant transmission project in Bihar to evacuate 2,400 MW of power from Adani Power's upcoming Pirpainti Ultra Super Critical Thermal Power Plant. The project, won through Tariff Based Competitive Bidding (TBCB), will involve constructing 881 ckm of transmission lines and 3,160 MVA of transformation capacity. Implemented via SPV Vikramshila Power Transmission Ltd., it is expected to be commissioned by Q4 2028. This win adds to AESL's transmission capex, now standing at approximately ₹91,500 crore, and is projected to generate an annual tariff of around ₹500 crore upon commissioning. The project aims to strengthen Bihar's transmission network and enhance supply reliability.

Key Highlights

  • AESL wins Bihar transmission project for 2,400 MW power evacuation.
  • Project involves 881 ckm transmission lines and 3,160 MVA transformation capacity.
  • Expected annual tariff of ~₹500 crore upon commissioning.
  • Transmission capex increases to ~₹91,500 crore.
  • Project to be delivered by Q4 2028.