StockWatch
·
Power - Transmission
Project Update27 Jun 2026, 09:30 am

Power Grid Corp: Transmission Project Commissioned in Andhra Pradesh

AI Summary

Power Grid Corporation of India Ltd has announced the complete commissioning of its transmission project, 'Transmission scheme for Solar Energy Zone in Ananthpuram (Ananthapur) (2500 MW) and Kurnool (1000 MW), Andhra Pradesh'. The project achieved commercial operation effective June 24, 2026, with the Notification for Commercial Operation (DOCO) received on June 25, 2026. This project was initially managed by POWERGRID Ananthpuram Kurnool Transmission Limited, a former wholly-owned subsidiary, which has since been amalgamated with POWERGRID Khawda II-C Transmission Limited as of March 1, 2026.

Key Highlights

  • Transmission project in Andhra Pradesh fully commissioned.
  • Commercial operations began on June 24, 2026.
  • Project capacity includes 2500 MW in Ananthpuram and 1000 MW in Kurnool.
  • Amalgamation of subsidiary completed effective March 1, 2026.