Downgraded FY27 growth target from 10–15% (prior call) to 'up to 10%'; H1 revenue down 11% YoY vs growth promise.
Cautiously Optimistic
next 1–2 quarters
Optimistic
multi-year
Strong ₹12.5k Cr order book and 18.9 GW O&M portfolio underpin long-term optionality, but Q2's 12.6% YoY revenue miss, stalled execution on 40% of order book, and downgraded FY27 guidance (10-15% → up to 10%) expose near-term delivery risk. Domestic margin pressure and rising costs inflate risk; Reliance ramp timeline undefined.
₹1527.5 Cr
Revenue · −12.6% YoY₹16.8 Cr
Reported PAT · +103.5% YoYCompressing
Margins · vs guidance: OverstatedDid the claims hold up?
Gross margin improved to 9.2% from 8.9%
METQ2 gross margin 9.2%, verified; but absolute margins thin at 3.7% EBITDA
Q2 is transition; Q3 & Q4 will be heavily loaded
OVERSTATEDH1 revenue -11% YoY; 4 Indian + 4 international projects stalled, not yet started
O&M grew 55% in Q2 to ₹99 Cr; portfolio now 18.9 GW
METO&M ₹99 Cr confirmed; portfolio growth real; but still only 6.5% of Q2 revenue
Order book ₹12,481 Cr; 34% higher than a year ago
PartialOrder book verified; but 40% of April 2026 base still stalled, revenue realization delayed
Maintaining 10% growth guidance for FY27
MISSPrior guidance 10-15% ex-Reliance; now 'up to 10%'—this is a downgrade; H1 delivered -11% YoY
Earnings quality
What changed since the last call
Revenue growth guidance downgrade
DowngradePrior call: 10–15% ex-Reliance. This call: 'up to 10%.' Delivered H1 -11% YoY; 4 projects stalled.
Project execution timeline slip
DowngradeExpected project starts in mid-Q2 per prior outlook; now revealed 4 Indian + 4 international not yet started; LOA/NTP delays cited.
O&M portfolio expansion
UpgradePortfolio grew 18.9 GW, up from 13.5 GW in March; O&M grew 48% in H1 to ₹183 Cr; now 50–50 mix with EPC in order book.
Domestic competitive intensity
DowngradeCK Thakur acknowledges margin pressure, ALMM/domestic cell constraints, and expects consolidation; smaller players to exit.
The Q&A
Sameer Dalal (Natarval & Sons) pressed aggressively on execution—'profitability is getting affected' by delays—and cost trajectory. CK Thakur held to 'we are on track' but conceded 4 projects stalled. Analysts skeptical; tone defensive, not reassuring.
Execution delays & margin impact — Sameer Dalal, Natarval & Sons
Partial4 projects from Coal India/NTPC not signed yet; 4 international delayed by financing. Egypt Minya project moving, NTP received. Q1 was subdued, Q2 also slowed, but Q3/Q4 heavily loaded. International revenue will keep adding.
Cost stabilization path — Sameer Dalal, Natarval & Sons
PartialRecurring overheads ₹79–84 Cr/quarter, almost flat. As % of revenue looks high now, but when revenue increases, leverage will help. Costs will increase when Reliance orders start, but proportionally not burdening overall cost.
FY27 growth target execution path — Disha, Sapphire Capital
Partial4 projects 40% of April 1 order book will contribute. Q3 & Q4 will not be in same proportion as Q1–Q2; they will be heavily loaded. On track. International projects all signed off now.
EBITDA margin sustainability — Disha, Sapphire Capital
AnsweredYes. Minimum requirement to maintain right. Execution will scale up in second half.
O&M business model & margin — Nilesh Doshi, Prospero Tree AMC
AnsweredO&M mix: 50% from own EPC, 50% from third party. GP ~20%, EBIT lower due to labor intensity. Cost ₹100k–150k per MW peak depending on scope. International margins 30–40% higher than domestic. O&M steady recurring income with low overheads.
Guidance status—raised, cut, or maintained? — Jayesh Shroff, Cask Capital
DodgedOur range was 10% to 15%. I still say 10%. It's not 0%, not between 0% and 1%. It will be around 10%.
Banking & consolidation outlook — Faisal Hawa, HG Hawa & Co
AnsweredConsolidation will happen. Financial qualification stringent now. Large-order PSUs coming with module prices low. Small players cannot compete. Expect consolidation in Q3–Q4. Industry not ready yet; many policies to implement. Expect healthy outcome once cell capacity stabilizes.
O&M international geography expansion — Saurabh Srivastava, Arista Consulting
AnsweredCurrently ~5% of total revenue. May grow to 10%. Gross margin ~20%, EBITDA translates with minimal overhead change. Target Africa, Saudi Arabia, Europe (Spain/Italy). O&M pipeline growth 25% this year to 22–25 GW.
Guidance
FY27 revenue growth 'up to 10%' ex-Reliance
MediumDowngraded from prior 10–15% ex-Reliance. H1 delivered –11% YoY; H2 ramp unproven. 4 projects stalled.
Q3 & Q4 FY27 heavily loaded; expect significant ramp
Low4 Indian + 4 international projects yet to start. Reliance timeline undefined. Egypt execution depends on monsoon completion.
EPC gross margin 8–10%; O&M gross margin ~20%
HighQ2 domestic EPC margin tracking low end; international margins higher (30–40% above domestic). O&M margin 23% this quarter, settling to ~20%.
Full-year EBITDA margin 4–4.5%
MediumQ2 EBITDA 3.7%; overheads flat at ₹84 Cr despite lower revenue. Margin improvement dependent on revenue ramp.
No explicit capex guidance; credit lines expanded ₹2,800 Cr this year
MediumCurrent credit line utilization ~70%. New sanctioned lines from Indian banks + South Africa bank for LC/BGs.
Risks the call surfaced
Execution
High4 Indian projects (Coal India, NTPC) + 4 international awaiting NTP/financing. Each month of delay costs ~₹200 Cr potential revenue (annualized). Analyst Sameer Dalal pressed: 'When will projects start?'
Margin
HighALMM cell constraint drives domestic modules scarce and costly; developers reworking bids, delaying awards. Entry barriers low; PSU orders coming with lower pricing. CK Thakur: 'competitors have bid below cost' in some cases; developers avoiding low-margin bids.
Revenue
HighH1 delivered ₹3,118 Cr (–11% YoY). Guidance requires 10% FY27 growth = ~₹1,700 Cr avg per half; H2 needs substantial ramp. But 4 Indian + 4 intl projects not yet started. Reliance timeline undefined. Egypt project monsoon-dependent.
Financing
MediumRecurring overheads flat at ₹84 Cr despite lower revenue (5.5% of sales vs prior 4.5–5%). Interest cost increasing due to LC extension + new credit lines. If revenue ramp fails, cost-to-sales ratio will expand, further compressing EBITDA margin.
Macro/Sector
MediumIndian mandate for domestic cell use (ALMM-II) raises project costs 15–17%, delaying awards. Rajasthan/Gujarat grid constraints curtailing solar output. BESS orders at risk as batteries cost-prohibitive; consolidation expected. Government policies still rolling out.
Management
Score 5/10. Evasive on project delays; uses phrases like 'on track' without specifics. Responsive on financials (CFO precise). CK Thakur candid on industry headwinds but defensive on execution timelines. Q&A suggests analysts distrust management's 'all fine' narrative. Missed prior call's H2 ramp promise (H1 down 11% YoY). Downgraded FY27 growth guidance 10–15% → 10%. 4 Indian + 4 intl projects stalled. Credibility grade C.
1 · Q3–Q4 FY27
West Minya (Egypt) project ramp-up; 4 stalled domestic + international projects initiation
2 · H2 FY27
Reliance order execution commencement; Adani framework 1.2 GW closure expected this month/early Nov
3 · FY27-end
Cell capacity stabilization in India (100 GW by Dec 2027); competitive consolidation expected
Domestic margin pressure and rising costs inflate risk; Reliance ramp timeline undefined.