StockWatch
·
Holding Company
Project Update17 Nov 2026, 08:50 pm

ACME Solar Commissions 52.32 MW BESS Component

AI Summary

ACME Solar Holdings Ltd (ASHL), through its subsidiary ACME Greentech Seventh Private Limited, has commissioned an additional 52.32 MW / 209.28 MWh of Battery Energy Storage System (BESS) capacity. This is part of a larger 300 MW / 1200 MWh project in Bikaner, Rajasthan. The Commercial Operation Date (COD) for this segment is November 19, 2026. With this addition, the subsidiary has achieved a cumulative commissioned BESS capacity of 247.67 MW / 990.68 MWh. The project has a Power Purchase Agreement (PPA) with SJVN Limited.

Key Highlights

  • ACME Solar commissioned an additional 52.32 MW BESS capacity.
  • Cumulative BESS capacity now stands at 247.67 MW.
  • Project located in Bikaner, Rajasthan, with PPA from SJVN Limited.
  • Commercial operations for the new capacity begin November 19, 2026.