Project Update18 Jun 2026, 04:20 pm

Borana Weaves: 9.9 MW Hybrid Project Commissioning Delayed to Aug 2026

AI Summary

Borana Weaves Ltd has announced a revised commissioning timeline for its 9.9 MW Hybrid Power Project in Kalikanagar, Gujarat. The project, developed by Clean Max Enviro Energy Solutions Limited, was initially expected to be operational by May 31, 2026. However, due to unforeseen factors including high wind speeds halting wind turbine erection, fuel shortages, and delays in obtaining necessary power line shutdowns, the commissioning is now tentatively rescheduled for the end of August 2026. This delay impacts the project's original schedule.

Key Highlights

  • 9.9 MW Hybrid Power Project commissioning delayed.
  • New tentative completion date is end of August 2026.
  • Original target date was May 31, 2026.
  • Delays attributed to external factors like weather and infrastructure.