Legal21 Aug 2026, 02:26 pm
Mahindra Lifespace Resolves ₹32.96 Cr Dispute with Parekh & Brothers
AI Summary
Mahindra Lifespace Developers Ltd has resolved a dispute with Parekh & Brothers, which had filed a Statement of Claim for ₹32.96 Crores as part of an arbitration process. The claim included ₹22.22 Crores for delay compensation. The company contested the claim and filed a counter-claim. The matter was amicably resolved with a Final Award passed on July 27, 2026. The settlement has no material impact on the company's financial position, with parties agreeing to comply with their respective obligations by the end of September 2026. The disclosure was made immediately upon receipt of the certified award copy.
Key Highlights
- Dispute with Parekh & Brothers for ₹32.96 Crores amicably resolved.
- Claim included ₹22.22 Crores for delay compensation.
- Company contested claim and filed counter-claim.
- Final Award passed on July 27, 2026, with no material financial impact.
- Parties to fulfill obligations by end of September 2026.
Price Impact
More from MAHLIFE