StockWatch
·
Power Generation
Project Update7 Jul 2026, 09:40 pm

NTPC Green Energy Adds 50.4 MW Wind Capacity in Gujarat

AI Summary

NTPC Green Energy Ltd announced that the first part capacity of 50.4 MW of its Vanki Wind Energy Project in Gujarat has commenced commercial operations effective July 8, 2026. This addition increases the total installed capacity of the NTPC Green Energy Limited Group to 10,721.80 MW. The current commercial capacity of the group stands at 10,671.40 MW. This development marks a step in the company's renewable energy expansion efforts.

Key Highlights

  • 50.4 MW wind capacity commissioned in Gujarat.
  • Commercial operations begin July 8, 2026.
  • Total group capacity increases to 10,721.80 MW.
  • NTPC Green Energy's current capacity is 10,671.40 MW.