Project Update30 Jun 2026, 12:48 pm
NTPC Ramagundam Solar Project Fully Operational at 176 MW
AI Summary
NTPC Ltd announced that the third and final part capacity of 41.6 MW from its Solar PV Project at Ramagundam, Telangana, has commenced commercial operation as of June 30, 2026. This brings the entire 176 MW project online, with the first two parts (100 MW and 34.4 MW) having started operations on May 2, 2026, and May 29, 2026, respectively. Following this commissioning, NTPC group's total installed capacity has reached 90,899 MW, with a commercial capacity of 89,819 MW. This expansion contributes to NTPC's overall renewable energy portfolio and installed capacity.
Key Highlights
- NTPC's 176 MW Ramagundam Solar Project is now fully operational.
- The final 41.6 MW capacity achieved commercial operation on June 30, 2026.
- Total installed capacity of NTPC group now stands at 90,899 MW.
- Commercial capacity increased to 89,819 MW with project completion.