Legal24 Jan 2026, 06:21 pm
OM Infra Ltd Contracts Terminated by NHPC Limited for Dibang Multipurpose Projects
AI Summary
OM Infra Limited has been informed about the termination of contracts awarded by NHPC Limited for the Dibang Multipurpose Projects (2880 MW) in Arunachal Pradesh. The termination is due to prevailing site conditions causing significant delays in erection activities under Lot-5B, beyond NHPC's control. The contracts have been terminated in accordance with the General Conditions of Contract Sub clause 42.1 - Termination for Employer’s Convenience. The Performance Security submitted by OM Infra or its sub-contractor will be duly discharged.
Key Highlights
- OM Infra Ltd contracts terminated by NHPC Limited for Dibang Multipurpose Projects
- Termination due to significant delays in erection activities under Lot-5B
- Delays caused by prevailing site conditions beyond NHPC's control
- Contracts terminated in accordance with General Conditions of Contract Sub clause 42.1
- Performance Security to be duly discharged