KEI Q2FY27: Revenue up 39% YoY to ₹3,776 Cr, PAT misses Street as EPC swings to loss
PAT +28.96% YoY · revenue +38.52% · margins compressing · miss vs street
₹3,776.42 Cr
+38.52% YoY
₹262.45 Cr
+28.96% YoY
6.9%
-0.4pp YoY
₹27.45
KEI Industries posted consolidated revenue of ₹3,776.42 Cr for Q2FY27, up 38.5% YoY (+18.6% QoQ) and well ahead of our pre-result preview band of ₹3,270–3,320 Cr. Consolidated PAT of ₹262.45 Cr grew 29.0% YoY but fell 4.3% QoQ, and came in 24–28% below the ₹343–364 Cr pre-result estimate — a clear miss on the bottom line even as the top line beat. Basic EPS was ₹27.45, down from ₹28.68 in Q1FY27 but above ₹21.30 a year ago.
Q2 FY-2027 vs prior quarters
The miss traces to the EPC Projects segment, which swung to a segment loss of ₹8.93 Cr versus a ₹5.13 Cr profit in Q2FY26, dragging consolidated net segment results even as the core Cables & Wires business grew revenue 39.7% YoY to ₹3,685.22 Cr with segment margin steady-to-better at ~11.3% (from ~10.9% a year ago). Layered on top, finance costs rose 20% YoY to ₹103.3 Cr and depreciation rose 51% YoY to ₹30.6 Cr as capital work-in-progress (₹1,271.9 Cr, roughly double the ₹634 Cr segment-asset base a year ago) builds out the Sanand and new Salarpur capacity. Net result: consolidated net margin slipped to roughly 6.9% of revenue, down from 8.55% in Q1FY27 and 7.35% in Q2FY26 (per our records) — a YoY and QoQ compression, since PAT grew slower than revenue on both counts.
The stock went into the print at ₹4,230.4, down 9% over the past month of trading.
For context: revenue is at a 6-quarter high.
FY27 revenue >20% (hedged; management says likely >25%, down from prior 25-30%). Operating margins 11-12% range (raised from prior 10.5-11%). Sanand FY27 ₹1,500-2,000 Cr (vs media-claimed ₹3,000 Cr, corrected). Annual capex ₹600-700 Cr/year for next 3-4 years, new Salarpur ₹700 Cr project announced.
— This quarter: beat
Against management's own guidance, the quarter is ahead: H1FY27 revenue grew 31.0% YoY to ₹6,961.76 Cr, above the raised >25% FY27 revenue bar (up from an original >20%), and H1 segment-result margin of ~11.9% of revenue from operations sits inside the raised 11–12% operating-margin guidance band — so on management's own metrics this reads as on-track-to-beat, even though it missed our Street-level PAT estimate. No standalone management press release was available for this filing to cross-check framing beyond the board-meeting letter and the financial statements themselves. Within this quarter's other developments, the GST demand was reduced by ₹4.46 Cr (immaterial to the P&L) and the company received a separate ₹17.1 lakh GST demand order; neither is financially significant. More material is the Income-Tax search conducted in May 2026, which the auditors' limited review flags again this quarter as unresolved, with impact 'not ascertainable' — a disclosed but unquantified overhang. The ₹2,000 Cr QIP from November 2024 continues to fund the capacity build, with ₹162.9 Cr still unutilised and parked in bank deposits/monitoring account.
W1
EPC Projects segment — can it return to profit after this quarter's ₹8.93 Cr segment loss?
W2
Operating margin trajectory vs management's raised 11-12% guidance band as Sanand capacity ramps (H1 running ~11.9% on a segment-result basis).
W3
Quantification of the Income-Tax search impact, flagged by auditors as 'not ascertainable' since May 2026.
Consolidated = standalone (associate KEI Cables SA Pty Ltd, South Africa, reported Nil profit/loss, certified by management as immaterial). No exceptional items either period. Auditors flag an unresolved Income-Tax search at company premises since May 2026 with impact 'not ascertainable'; current tax includes ₹5.88 Cr of earlier-years tax, deferred tax net of ₹5.61 Cr earlier-years DTA.