Project Update29 Aug 2026, 07:30 pm

Borana Weaves: 9.9 MW Hybrid Project Commissioning Delayed

AI Summary

Borana Weaves Ltd has announced a revised commissioning timeline for its 9.9 MW Hybrid Power Project in Kalikanagar, Gujarat. The project, originally expected by August 31, 2026, will now see partial commissioning of one WTG location with the 7.65 MW solar component by September 30, 2026. The remaining two WTG locations are now tentatively scheduled for commissioning by the end of October 2026. The delays are attributed to external factors including high wind speeds affecting WTG erection, heavy monsoon conditions necessitating road rework, and delays in obtaining necessary shutdowns for transmission line work from various authorities.

Key Highlights

  • 9.9 MW Hybrid Power Project commissioning timeline revised.
  • Partial commissioning by September 30, 2026; full by October 2026.
  • Delays caused by weather and infrastructure access issues.
  • Company to keep stakeholders informed of further developments.