Tata Power commissions 400kV Jalpura-Khurja transmission corridor

AI Summary

Tata Power has successfully commissioned the second element of its Jalpura-Khurja Transmission Project in Uttar Pradesh. This includes a 400 kV double-circuit transmission line spanning 162 circuit kilometers and a 400/220 kV GIS substation at Jalpura with 1,000 MVA transformation capacity. Executed by its wholly-owned subsidiary, TP Jalpura Khurja Power Transmission Limited, the project strengthens power transmission infrastructure in NCR and Western Uttar Pradesh, enhancing connectivity to demand centers. This commissioning reinforces Tata Power's role in building a robust electricity grid and expands its operational transmission portfolio to 7900 circuit kilometers.

Key Highlights

  • Commissioned 162 CKM of 400kV double-circuit transmission line.
  • Added a 1,000 MVA, 400/220 kV GIS substation at Jalpura.
  • Strengthens power infrastructure for NCR and Western Uttar Pradesh.
  • Tata Power's transmission portfolio now stands at 7900 CKM.